Once the project logistics and sequence have been analyzed and the engineering drawings have been coordinated with all trades involved, Coastal then employs the Short Interval Production Planning (SIPP) process for the duration of the project. Beginning with priority wall identification and coordination, the SIPP process takes a weekly “look-ahead” for the next three weeks and detailed manpower and supplies are scheduled. This process offers tremendous advantages by not only ensuring the schedule, but also by actively driving the project.
Our staff is involved from the beginning of the project, and they lead the commissioning process by coordinating with the construction manager, electrician, temperature controls contractor, test and balance and of course, the owner and inspectors.